| # | Child Code | Parent Code | Job Number |
| 1 | not ordered in timely fashion | Material | 04 |
| 2 | worked on pm function | Task Not Proprerly Planned | 04 |
| 3 | worked on pm function | Task Not Proprerly Planned | 04 |
| 4 | had to fix conduits that were backfilled around incorrectly | Other Trades | 04 |
| 5 | unscheduled meeting request | Task Not Proprerly Planned | 04 |
| 6 | relocate to other hec job | Other | 04 |
| 7 | working time changed | Unscheduled Requests from GC | 04 |
| 8 | working time changed | Unscheduled Requests from GC | 04 |
| 9 | weather good enough to continue on chilling tower | Weather | 02 |
| 10 | work needed to be completed on lvl 1 | Task Not Proprerly Planned | 02 |
| 11 | able to work all day outside | Other | 02 |
| 12 | rain | Weather | 02 |
| 13 | rain | Weather | 02 |
| 14 | more difficult than originally assessed | Task Not Proprerly Planned | 04 |
| 15 | more difficult than originally assessed | Task Not Proprerly Planned | 04 |
| 16 | worked on more urgent tasks | Other | 02 |
| 17 | ww installed doors without holes for security | Other Trades | 02 |
| 18 | temp for elevators | Unscheduled Requests from GC | 02 |
| 19 | wrong ground ordered | Task Not Proprerly Planned | 02 |
| 20 | overcoming hidden conditions - did not plan for using heat blanket | Other | 02 |
| 21 | Relocate to do other work | Area Not Ready | 04 |
| 22 | Relocate to do other work | Area Not Ready | 04 |
| 23 | Relocate to do other work | Area Not Ready | 02 |
| 24 | Not having material | Material | 02 |
| 25 | Not having material | Material | 02 |
| 26 | Not having material | Material | 04 |
| 27 | Not having material | Material | 03 |
| 28 | Preparing areas for other contractors, or our own subs | Other Trades | 02 |
| 29 | Preparing areas for other contractors, or our own subs | Other Trades | 02 |
| 30 | Not having Rental Equipment in the right | Area Not Ready | 02 |
| 31 | Not having Rental Equipment in the right | Area Not Ready | 02 |
| 32 | Not having Rental Equipment in the right | Area Not Ready | 02 |
| 33 | Not having Rental Equipment in the right | Area Not Ready | 02 |
| 34 | Manpower - getting the Guys on Site | Absenteeism | 02 |
| 35 | Manpower - getting the Guys on Site | Absenteeism | 02 |
| 36 | Waiting for other subs | Other Trades | 02 |
| 37 | Waiting for other subs | Other Trades | 02 |
| 38 | Waiting for other subs | Other Trades | 02 |
| 39 | Waiting for other subs | Other Trades | 02 |
| 40 | Waiting for other subs | Other Trades | 02 |
| 41 | Waiting for other subs | Other Trades | 04 |
| 42 | Manpower - having appropriate skill level | Task Not Proprerly Planned | 02 |
| 43 | Manpower - having appropriate skill level | Task Not Proprerly Planned | 03 |
| 44 | Manpower - having appropriate skill level | Task Not Proprerly Planned | 03 |
| 45 | Manpower - having appropriate skill level | Task Not Proprerly Planned | 03 |
| 46 | Manpower - having appropriate skill level | Task Not Proprerly Planned | 04 |
| 47 | unplanned coordination with other subs | Other Trades | 04 |
| 48 | prefab delivery issue | Material | 04 |
| 49 | unplanned material delivery | Material | 04 |
| 50 | work area blocked | Other Trades | 03 |
| 51 | work area blocked | Other Trades | 03 |
| 52 | work area blocked | Other Trades | 03 |
| 53 | late start on pathway | Other | 03 |
| 54 | work around material staged on floor | Other Trades | 03 |
| 55 | locations missed on prints roughed in | Other | 03 |
| 56 | waiting on turner | Other Trades | 03 |
| 57 | rework | Area Not Ready | 03 |
| 58 | late start pulling cable | Other | 03 |
| 59 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 60 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 61 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 62 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 63 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 64 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 65 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 66 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 67 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 68 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 69 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 70 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 71 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 72 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 73 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 74 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 75 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 76 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 77 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 78 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 79 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 80 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 81 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 82 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 83 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 84 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 85 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 86 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 87 | insufficient information from holmes | Other | 04 |
| 88 | insufficient information from holmes | Other | 04 |
| 89 | unexpected jpac walk with superintendent | Other | 04 |
| 90 | unexpected jpac walk with superintendent | Other | 04 |
| 91 | missing dsiconnects | Material | 02 |
| 92 | worked 6:30 - 2 pm per turner | Other | 02 |
| 93 | trying different method of attaching stiffy underfloor mc brackets | Tool or Equip. Breakdown | 02 |
| 94 | finish friday project and help lighting crew | Other | 02 |
| 95 | change conduit support at north comm | Unscheduled Requests from GC | 02 |
| 96 | changed task - rough in level 2 | Task Not Proprerly Planned | 02 |
| 97 | gc decided to pour remaining cdf tomorrow | Other | 02 |
| 98 | forms not built | Other Trades | 02 |
| 99 | framing in way of can locations | Other Trades | 02 |
| 100 | waiting for reframing of roughed in walls | Area Not Ready | 02 |
| 101 | waiting on information | Other | 02 |
| 102 | waiting on information | Other | 02 |
| 103 | waiting on information | Other | 02 |
| 104 | material did not arrive as planned | Material | 04 |
| 105 | material did not arrive as planned | Material | 04 |
| 106 | did not have the proper tools | Tool or Equip. Breakdown | 04 |
| 107 | moved to 3rd floor - rough-in core | Unscheduled Requests from GC | 02 |
| 108 | moved to 3rd floor - rough-in core | Unscheduled Requests from GC | 02 |
| 109 | held up by framing issues | Other Trades | 02 |
| 110 | unexpected request from superintendent | Other | 04 |
| 111 | unexpected request from superintendent | Other | 04 |
| 112 | unexpected request from superintendent | Other | 04 |
| 113 | sprinkler pipe in way of projection screen install | Other Trades | 02 |
| 114 | framing not complete | Area Not Ready | 04 |
| 115 | framing not complete | Area Not Ready | 02 |
| 116 | ups room flooring rescheduled | Other Trades | 02 |
| 117 | able to work in areas not available tuesday | Task Not Proprerly Planned | 02 |
| 118 | sealer on floor(wet) | Other Trades | 02 |
| 119 | pcs sheetrocking cardio room | Other Trades | 03 |
| 120 | better than expected results | Task Not Proprerly Planned | 04 |
| 121 | pcs wall framed too far west in nw quad conf room, had to re rough-in | Other Trades | 02 |
| 122 | relocate f33 fixtures | Unscheduled Requests from GC | 02 |
| 123 | forming and pouring concrete blocked access | Other Trades | 02 |
| 124 | last task took longer than anticipated | Other | 02 |
| 125 | lost apprentice rest of week (heard about on monday) | Absenteeism | 02 |
| 126 | last task incomplete jw go back and complete | Other | 02 |
| 127 | unpack premature; whips - plan not agreed upon | Task Not Proprerly Planned | 02 |
| 128 | need to pull cable on 3rd floor & 2nd floor | Other | 02 |
| 129 | multi jam | Tool or Equip. Breakdown | 02 |
| 130 | redirected to other tasks | Task Not Proprerly Planned | 02 |
| 131 | multi tool problems | Tool or Equip. Breakdown | 02 |
| 132 | too much scheduled | Task Not Proprerly Planned | 02 |
| 133 | too much scheduled | Task Not Proprerly Planned | 04 |
| 134 | multi jam | Tool or Equip. Breakdown | 02 |
| 135 | redirected to other tasks | Task Not Proprerly Planned | 02 |
| 136 | redirected to other tasks | Task Not Proprerly Planned | 02 |
| 137 | redirected to other tasks | Task Not Proprerly Planned | 02 |
| 138 | framing needs to be corrected to accomodate fixture housing | Other Trades | 02 |
| 139 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 140 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 141 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 142 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 143 | not excavated yet or only partially excavated | Area Not Ready | 02 |
| 144 | sidetracked doing temp pwr & fire caulking | Other | 02 |
| 145 | fcu combo on lvl 2, rough in rpo data counter | Other | 02 |
| 146 | framing needs to be corrected to accommodate fixture housing | Other Trades | 02 |
| 147 | framing needs to be corrected to accommodate fixture housing | Other Trades | 02 |
| 148 | not enough 8 foot ladders | Tool or Equip. Breakdown | 02 |
| 149 | crew saturday used up prepared material | Task Not Proprerly Planned | 02 |
| 150 | projector screen post setups took longer | Other | 02 |
| 151 | projector screen post setups took longer | Other | 02 |
| 152 | plenum ceilings in hallway | Unscheduled Requests from GC | 02 |
| 153 | dan class, not factored in scehdule | Task Not Proprerly Planned | 02 |
| 154 | short on mc | Material | 02 |
| 155 | redo conduit | Other | 02 |
| 156 | apex closed off roof | Other Trades | 02 |
| 157 | not able to go over six feet on ladders | Other | 03 |
| 158 | matt sick | Weather | 02 |
| 159 | matt sick | Weather | 02 |
| 160 | help with lights - data center | Other | 02 |
| 161 | added fire alarm wiring required | Other Trades | 04 |
| 162 | manpower pulled off yesterday afternoon | Absenteeism | 04 |
| 163 | waiting for ceiling grid opening to be cut for fixtures | Area Not Ready | 02 |
| 164 | no access due to flooring installation | Other Trades | 02 |
| 165 | unusually cold weather | Weather | 02 |
| 166 | unusually cold weather | Weather | 02 |
| 167 | unusually cold weather | Weather | 02 |
| 168 | gc directed other temp power needs | Other | 02 |
| 169 | task taking longer than anticipated | Other | 02 |
| 170 | work in data center to move gutters | Other | 02 |
| 171 | door blocked by crane | Other Trades | 02 |
| 172 | l2 & l3 pulled off tasks to install temp lighting restrooms | Other | 02 |
| 173 | ceiling grids only partially done | Area Not Ready | 02 |
| 174 | ceiling grids only partially done | Area Not Ready | 02 |
| 175 | ceiling grids only partially done | Area Not Ready | 02 |
| 176 | late delivery | Material | 02 |
| 177 | wrong coring layout by g.c. for cube power - data - f.a./ had to remove raceways & get new holes then re-pipe | Other | 02 |
| 178 | wrong coring layout by g.c. for cube power - data - f.a./ had to remove raceways & get new holes then re-pipe | Other | 02 |
| 179 | s.w. entry ada door motor set wrong , therefore while removing grout to reset they damaged raceways & wiring . will have to replace | Other Trades | 02 |
| 180 | Waiting for other subs | Other Trades | 6050MH |
| 181 | Relocate to do other work | Area Not Ready | 6050MH |
| 182 | working time changed | Unscheduled Requests from GC | 6050MH |
| 183 | ice | Weather | 01 |
| 184 | ice | Weather | 02 |
| 185 | rain | Weather | 01 |
| 186 | weather good enough to continue on chilling tower | Weather | 6050MH |
| 187 | lost apprentice rest of week (heard about on monday) | Absenteeism | 6050MH |
| 188 | prefab delivery issue | Material | 6050MH |
| 189 | rained today | Weather | 05 |
| 190 | rained today | Weather | 01 |
| 191 | off early, ill | Absenteeism | 01 |
| 192 | Not having material | Material | 01 |
| 193 | not enough 8 foot ladders | Tool or Equip. Breakdown | 01 |
| 194 | matt sick | Weather | 01 |
| 195 | ice | Weather | 01 |
| 196 | manpower pulled off yesterday afternoon | Absenteeism | 01 |
| 197 | Waiting for other subs | Other Trades | 01 |
| 198 | framing not complete | Area Not Ready | 01 |
| 199 | ordered wrong | Material | 01 |
| 200 | rain | Weather | 351120018 |